Test Installation Project
1,600 CFM moved outside the building in a single weekend.
Capacity
1,600 CFM
Footprint
40 ft enclosure
Downtime
1 weekend
Delivered
2025
The plant had outgrown a compressor room wedged between two production lines. Heat was rejecting into the workspace, service access required shutting down a cell, and there was no room left for the capacity the next contract demanded.
We scanned the room and the exterior tie-in area, then designed a modular enclosure sited on a new pad forty feet from the wall. The unit was built, wired, and tested in the shop, set with a crane, and cut over during a scheduled weekend shutdown. The vacated room became staging space.
Spec Info Here
Week 1
Scan and assessment
Point cloud of compressor room, exterior wall, and pad location.
Weeks 2–3
Design approval
CAD layout and equipment selection reviewed with plant engineering.
Weeks 4–9
Shop build
Enclosure fabricated, equipment set, piping and electrical completed.
Week 10
Factory test
Controls, ventilation, and leak testing verified before shipment.
Week 11
Set and cut-over
Crane set Saturday, tie-in and start-up complete by Sunday night.